The
office complex, dressing room, youth and senior teams’ hostels being
constructed by Kumasi Asante Kotoko at Adako Jachie are in near ruins as weeds
have engulfed the two structures which have stalled in the last five months.
Numerous
calls and passionate appeals by hundreds of Kotoko fans who have been asking about
the progress of work at the site moved me to visit the site last week. My first
observation was that work has stopped for months.
The
Projects, started in 2011, progressed until the resignation of the Executive
Chairman, Dr. K. K. Sarpong in July this year. Since then no work has gone on. Checks
with the Project Manager, George Amponsah-Duodu revealed that construction has stopped
because of the lack of funds.
Dr.
Sarpong in his handing over notes I have seen gave a rundown of events
concerning the project. He stated that the projects were “being undertaken by
direct labour under the supervision of D-Span Consult, an architectural firm in
Accra. Purchases of materials and services for the project [were] made by the
Project Manager, George Amponsah Duodu.
“The
office complex [was] at the flow level of the 1st floor of the 3-storey
building. After the initial hiccup suffered during construction due to
soil-type difference, works on the first floor [was] about 70% completed. What
[was] left before the concrete casting could be done [was] the dropping of the
floor bars by the steel benders which [was to take] about two weeks, upon
inspection by the engineers.
“Available
on site [was] enough chippings, sand and iron rods to complete the flow of the first
floor. The Youth Team Hostel, which is also a 3-storey building, [was] at the
lintel level. Monies spent so far on the projects, according to the Project
Manager amount to GHC 365,399.68 with GHC50, 317.68 going into consultancy and
the remainder representing monies spent on Project works” wrote the former
chairman.
At
the moment, the project has been left to the mercy of the weather and weeds.
Kotoko supporters who visit the training ground on daily basis have been
expressing concerns over the current state of the project. The appeal from these
fans, I interviewed is that, funds should be solicited to first clear the loads
of weeds that have engulfed structures.
Jerome, good blog. Regularly updated and informative. But we the readers would appreciate it if you add some video clips of some of the events you cover and include some audio, to make more multimedia.
ReplyDelete